Progress 03/01/24 to 02/28/25
Outputs Target Audience:
Nothing Reported
Changes/Problems:
Nothing Reported
What opportunities for training and professional development has the project provided?
Nothing Reported
How have the results been disseminated to communities of interest?
Nothing Reported
What do you plan to do during the next reporting period to accomplish the goals?Finalize the design plan for the Meat Technology Building renovation and expansion. Obtain approval from NIFA and the USG BOR for the selected construction contractor responsible for both design and construction
Impacts What was accomplished under these goals?
Fort Valley State University proposes two projects for the 2013-2017 1890 Facilities Grant Program: 1) remodeling and expanding the Ellison Agricultural Engineering Technology Building, and 2) expanding the Meat Technology Center (Animal and Food Science Building) with new research laboratories, classrooms, offices, and support areas. These projects address the need for additional and updated instructional, outreach, and research space. The university will first focus on the Ellison Agricultural Engineering Technology Building. Current efforts are directed towards renovating the Meat Technology Center. The design plan is being revised to utilize the remaining budget and NIFA station funds, expediting the design and construction schedule. The site is free from environmental issues. Approval has been granted to use station funds ($893,792.00) for project completion, and the USG-BOR has been notified. Scheduled CDs, including equipment and casework, will be reviewed by BOR and the campus for construction permit application. All necessary paperwork will be submitted to NIFA before proceeding further.
Publications
|
Progress 03/01/23 to 02/29/24
Outputs Target Audience:
Nothing Reported
Changes/Problems:The design firm recently detected several unforeseen structural issues in the crawlspace of the Kell Building that now require substantial adjustments to the design. Construction and material cost escalations have further complicated and delayed the process. Although the design was completed, itwas deemed essential to revise itto stay within the project budget. Once the design is finalized, it will be submitted to NIFA and the Board of Regents of the University System of Georgia (BOR) for review and approval before proceeding with construction planning. What opportunities for training and professional development has the project provided?
Nothing Reported
How have the results been disseminated to communities of interest?
Nothing Reported
What do you plan to do during the next reporting period to accomplish the goals?The BOR is closely monitoring thedesign revision and the cost to facilitate the project. As soon as the design is finalized, we will proceed with construction. Since the project does not involve ground-up construction, weanticipate the objective of Award No. 2019-45200-29221 to be accomplished within the next year. The budget available currently for the KellBuilding Project is $4,742,883.01 (see attached SF-425). This budget will be expended within thenext year.
Impacts What was accomplished under these goals?
The Facilities Project Concept Proposal for USG-BOR's Integrated Project Review was developed and submitted. The review was completed. A design firm has been selected, and the selection process and the firm have been approved by NIFA. State Historic Preservation approval has been secured and environment assessment has also been completed. A Project Team/Advisory Committee has been formed. The design firm has completed the final design plans; however, there was an unexpected structural issue detected that requires a small adjustment to be made to the design. Construction and material cost escalations have further complicated and delayed the process. It was deemed essential to revise the design plan to stay within the project budget. Once the design is finalized, it will be submitted to NIFA and the Board of Regents of the University System of Georgia (BOR) for review and approval before proceeding with construction planning. The progress made during the past year in chronological order is given below: January 31, 2023 - Cost estimate review with the design firm. February 13, 2023 - GMP team meeting. April 27, 2023 - GMP building stabilization plan review. October 10, 2023 - Cost-overrun and strategy discussion with the USG officials. The contractor selection process has been completed and the recommendations are currently being reviewed by the USG-BOR Facilities Office.
Publications
|
Progress 03/01/22 to 02/28/23
Outputs Target Audience:
Nothing Reported
Changes/Problems:Unforeseen building stability issues were discovered when the design team inspected the crawlspace of this historic building. In order to accommodate the additional expenses toward building stabilization, the design plan is currently being amended. The revised plan will be submitted to NIFA for review and approval. What opportunities for training and professional development has the project provided?
Nothing Reported
How have the results been disseminated to communities of interest?
Nothing Reported
What do you plan to do during the next reporting period to accomplish the goals?Finalize the design plan, seek approval from NIFA and the USG BOR, and proceed with construction planning.
Impacts What was accomplished under these goals?
The project has reached the final phase of the design process. A thorough evaluation conducted by the Georgia Environmental Protection Division has determined that the site will not be included in the Hazardous Site Inventory. Based on their assessment, there is no evidence to suggest any substance exceeding the reportable quantity on the property. Despite this positive outcome, progress on the project has slowed due to cost overruns. A revision to the scope of the project is being considered since the stabilization of this historic building is now estimated to cost more than what was initially budgeted. Once finalized, the plan will be submitted to NIFA for approval.
Publications
|
Progress 03/01/21 to 02/28/22
Outputs Target Audience:
Nothing Reported
Changes/Problems:Remediation steps are being planned to resolve the issue identified in the Environmental Study Report. What opportunities for training and professional development has the project provided?
Nothing Reported
How have the results been disseminated to communities of interest?
Nothing Reported
What do you plan to do during the next reporting period to accomplish the goals?Resolve the issue identified in the Environmental Study Report, and seek approval from NIFA to proceed with construction.
Impacts What was accomplished under these goals?
Contracting firm has been selected. The furniture placement plan, materials, and design have been finalized. Once the USG BOR Facilities Office completes all processes, we will share all documentswith NIFA to seek approval to proceed with construction and request release of funds.
Publications
|
Progress 03/01/20 to 02/28/21
Outputs Target Audience:
Nothing Reported
Changes/Problems:
Nothing Reported
What opportunities for training and professional development has the project provided?
Nothing Reported
How have the results been disseminated to communities of interest?
Nothing Reported
What do you plan to do during the next reporting period to accomplish the goals?Construction contractor will be selected and program and timeline will be finalized. Start initial preparation work for construction and renovation.
Impacts What was accomplished under these goals?
A design firm has been selected and design plans have been finalized. Currently in the process of reviewing the environmental study report and selecting a contracting firm.
Publications
|
Progress 03/01/19 to 02/29/20
Outputs Target Audience:
Nothing Reported
Changes/Problems:
Nothing Reported
What opportunities for training and professional development has the project provided?
Nothing Reported
How have the results been disseminated to communities of interest?
Nothing Reported
What do you plan to do during the next reporting period to accomplish the goals?For the next reporting period, we will complete the architectural plans for renovation and begin the construction work.
Impacts What was accomplished under these goals?
A project proposal concept document was developed as required by the University System of Georgia - Board of Regents for Integrated Project Review. The USG has completed the Integrated Project Review and has approved renovation of the Kell Building to establish the FVSU Center for Agricultural Innovation and Entrepreneurship. FVSU Facilities Director and the USG Facilties Office representative are currently working on bidding for architectural work.
Publications
|
|